The Sacramento County Water Agency is preparing to meet new water supply demands for decades to come with its first ever surface water treatment plant. Named after its historical region, the Vineyard Surface Water Treatment Plant will treat water from the Sacramento River that will be pumped from the Freeport intake facility, where it will be treated to the highest drinking water standards.

Project Information
Background information and timeline of the project.

Traffic and Construction
Up-to-date traffic and construction reports.

Photos
Monthly aerials of the construction site.

Contact Us
Contact the project manager.


Project Status Update
(As of 4/25/09)


Percent Complete

 
412/1352 = 30.5%
 
Start Date
 
March 10, 2008
 
Number of Working Days          

412


Contract Milestone (B)
(Completed: Nov. 2008)

View the complete list of
completed and existing milestones

Substantial completion of
the on-site drainage system
and storage basins
required to collect and treat
stormwater run-off.
 
Completion Date 

November 21, 2011


Sacramento County
Water Agency
9280 West Stockton Blvd, Suite 220
Elk Grove, CA 95758
916-875-1955
For more information, alternate formats or web operations saccodwr@saccounty.net.

© Copyright
Privacy Policy | Conditions of Use | Accessibility Policy