Construction will be ongoing Monday - Friday from 6 a.m. - 6 p.m. This page will house traffic and construction updates regarding the Vineyard Surface Water Treatment Plant. For more traffic and/or construction information, call (916) 876-8463 (VINE).

Traffic Updates

 There are currently no traffic updates.

Construction  Updates
  • Poured 21,000 cubic yards; this is 38% of the estimated 55,000 cubic yards.
  • Placed 50% of the rebar.
  • Clearwell slab on grade construction, column construction nearing 50% complete. Wall pours at south end of structure underway.
  • Storm water basin 1 and 2 are essentially complete and temporary treatment system is installed and ready for use. 
  • Flow distribution structure is nearly 50% complete. Anticipate connection to FRWA pipe stubs by February 2009. 
  • Plant drain pump station concrete is complete to finished grade. 
  • Flushing basin is complete.
  • Sludge overflow lagoon is 95% complete.
  • Floc/Sed basin slab on grade construction has begun with 16 sections
  • The slab on grade forming at the filters has begun. All under slab piping is installed and encased.
  • Duct bank construction is underway.

Sacramento County
Water Agency
9280 West Stockton Blvd, Suite 220
Elk Grove, CA 95758
916-875-1955
For more information, alternate formats or web operations saccodwr@saccounty.net.

© Copyright
Privacy Policy | Conditions of Use | Accessibility Policy